Construction The contractor is finishing up with the planter work in the brick courtyard.  However, for the next four business day, they will be making loud noises (jack hammer) from 9:00 am to 12:00 pm. Shopping Carts Please remember to return the cart when you are finished with it.  Also,

Continue reading

Belt’s Landing Pool Opening

The pool at Belt’s Landing is tentatively set to open at 12:00 pm on Wednesday, July 1st.  Due to COVID-19, there will be a number of restrictions in place to utilize the pool. Only residents of Belts Landing are permitted to use the pool.  Guests, absentee owners, and yacht club members are

Continue reading

Construction & Pool Opening

Construction Shawn Smith, Brian, and I met with project manager for the 701 balcony and the brick court yard planter.  Weather permitting, they will be finished with the balcony by the 19th and the planter by the 26th.  Shawn and I authorized them to work on Saturday (quiet work only) if