Belt’s Landing Schedule 5/11-5/15

Unit 701 Balcony activities are as follows:

 

5/11 – Window and door flashings and start installing EPS

 

5/12 – Continue installing EIFS

 

5/13 – Finish grinding thin-set off balcony. The grinder we brought to the site last week did not work.  There may be some moderate noise on this day.

 

5/14 – Continue installing EIFS

 

5/15- Continue installing EIFS

 