Activities are as follows:
5/4:
Window and door install
Starting EIFS install
No loud noises anticipated.
5/5:
Finish window and door install
Continue EIFS Install
No loud noises anticipated.
5/6:
Continue EIFS install
*Grind thin-set off balcony*- This will be an all day operation. We will break from 12pm – 1pm
5/7:
Continue EIFS install
No loud noises anticipated.
5/8:
Continue EIFS Install
No loud noises anticipated.