I spoke with the project engineer. The project is really at a point of no return. To stop now could expose the unit to the elements and we have no idea how long this stay at home order will last. I have asked that he try to get another crew out there and to stop work between 12pm to 1 pm.
4/20:
Chipping existing tile with hammer drill and hammers and chisels
4/21:
Weather dependent.
Chipping existing tile with hammer drill and hammers and chisels
4/22:
Chipping existing tile with hammer drill and hammers and chisels
4/23:
Chipping existing tile with hammer drill and hammers and chisels
4/24
Chipping existing tile with hammer drill and hammers and chisels
Please advise if this is an issue.
We are bringing EPS to the job so we can start installing EIFS. However, we cannot install to the deck until all the tile is removed.